An overview of Trace Logic in Primavera P6
Trace Logic is a Primavera P6 tool that lets you step, or “trace,” forward or backward through a series of activities to view and focus on their predecessor/successor relationships. It displays as a Bottom Layout in the Activities window and shows relationships for whichever activity you select in the Activity Table, Activity Network, Activity Usage Spreadsheet, or the Gantt Chart in the Top Layout. The selected activity appears as a box with a blue border so you can quickly focus on its relationships; critical activities appear with a red border. Lines connecting the boxes represent the relationships themselves.
Why use Trace Logic?
Project managers and schedulers use Trace Logic to review an activity’s predecessors and successors and understand why it is scheduled when it is, whether a delay came from a predecessor slipping or from a constraint still in effect. It is also a fast way to sanity-check whether relationship types actually reflect how the work should sequence, for example whether a Site Prep activity should have a start-to-start relationship with its Excavation successor rather than finish-to-start.
This tutorial covers displaying and customizing Trace Logic using a real example: an Excavation activity that started late, stalled mid-stream, and finished late against its baseline.
Step 1: Open a layout that shows the problem
Open a project and select a layout that compares current to baseline bars. In this example, activity BA2020 Excavation started late, shows a work stoppage as a “bar-neck,” and finished late compared to its baseline. Trace Logic is used next to see the possible impact on its successor activities.
Step 2: Display Trace Logic on the bottom layout
Go to View > Show on Bottom > Trace Logic.
Step 3: Select an activity and read its logic
With Trace Logic showing on the bottom, select an activity in the top layout, whether that is the Activity Table, the Gantt Chart, the Activity Network, or the Activity Usage Spreadsheet. Selecting BA2020 Excavation shows its predecessors and successors in Trace Logic below, making the possible downstream impact of its delay visible. The selected activity shows a blue border; critical-path activities, such as BA2030 and BA2040 in this example, show a red border. Zoom in and out to read the diagram and the contents of each activity box.

Reading critical activities, critical relationships, and driving relationships
- Activity boxes outlined in red are critical activities; boxes outlined in black are not critical.
- Solid red lines represent critical relationships; solid black lines represent non-critical relationships.
- Solid lines represent driving relationships; dashed lines represent non-driving relationships.
Step 4: Set how many levels of logic to show
Open View > Bottom Layout Options, or right-click inside the Trace Logic display and select Trace Logic Options, to open the Trace Logic Options dialog. Use it to specify how many levels of predecessors and successors are displayed.
Step 5: Control what each activity box shows
Trace Logic’s activity boxes use the same box template as the current Activity Network layout. Open View > Activity Network > Activity Network Options to control their contents.
Step 6: Choose or edit the box template
In the Activity Network Options dialog, select a box template to control what activity information appears in each box, and edit that template if you need different fields shown.
Step 7: Print the Trace Logic diagram
Open Print Preview from the toolbar, select the Page Setup Options tab, and check the Trace Logic box along with any other options you want, then preview and print.
Tip: Limit the number of predecessor/successor levels (Step 4) before printing; an unbounded Trace Logic diagram can print across far more pages than intended.
Want hands-on help mastering Primavera P6?
Mary Williams, a certified master instructor, teaches instructor-led Primavera P6 courses from basics through advanced and resource loading, built around how your team actually works.