An Introduction to Buffer Management

Asta PowerProject includes many exciting features to help you manage projects efficiently so that you complete your projects on time and within budget. Buffer Management is one of the features included in Asta PowerProject that helps you protect your strategic project deadlines. Buffer Management, based upon the Theory of Constraints (TOC) and Critical Chain Project Management (CCPM) concepts proposed by Dr. Goldratt in 1990, provides a method to more effectively manage activity durations. Buffer Management assists you in generating a project plan that protects you against uncertainties and reduces the impact of potential changes.

According to Andrew Willard, International Business Director of ASTA Development PLC, in his white paper “Using Asta PowerProject for Critical Chain and Buffer Management”: “Critical Chain is defined as the longest sequence of activities from several different paths, connected by activities performed by common resources. The contingency period in the Critical Chain is removed from individual activities and is utilized to create a project buffer. These buffers provide the necessary cushions to individual activities enabling them to accomplish the final goal of completing the Critical Chain in the least possible time”.

Buffer or contingency activities can be setup to protect important deadlines and reduce excess float. Buffer activities do not have float, and they shrink or expand in duration as required without moving beyond their finish date or the start date of the successor activities.

Asta PowerProject includes two types of buffer activities:

  • project buffers to protect a project finish date
  • feeder buffers to protect the start date of successor activities

According to Andrew Willard in the above mentioned white paper, the following steps should be performed when incorporating buffer activities and Critical Chain Project Management:

  1. Plan the schedule utilizing traditional Critical Path Method (CPM)
  2. Identify the protective duration estimate or cushion incorporated for each activity
  3. Determine the “reasonable” estimated duration for each activity
  4. Remove the cushion or safety estimates for each activity based upon steps 2 and 3.
  5. Identify the critical chain as the longest chain of dependent activities
  6. Add a “project buffer” at the end of the project
  7. Add “feeder buffers” in non-critical chains that merge into the critical chain
  8. Include resource buffers as necessary to ensure resource availability
  9. Verify the critical chain

This tutorial provides a very simple illustration of Buffer Management in Asta PowerProject.

Step 1: Start from a two-phase project

The project consists of 2 phases. Phase 1 is a non-critical path connecting to activities in Phase 2, which is the critical path. The activities in Phase 1 have significant float, which may indicate that safety or cushion duration has been included in those activities. The project finish date, which we want to protect, is April 4.

Step 2: Remove the cushion and add the buffers

The safety or cushion duration is removed from the activities in Phase 1 and a “feeder buffer” activity is added with a duration of 6 days; this buffer activity will expand or shrink based on the other activities in Phase 1, and it is connected to an activity in the critical path. The safety or cushion duration is also removed from the activities in Phase 2, and a “project buffer” of 20 days is added to the end of the project to protect the finish date of April 4.

Step 3: Watch the feeder buffer respond to a duration change

The duration of Phase 1 Task 3 is increased from 8 to 10 days. The duration of the Feeder Buffer task is reduced to 4 days from 6 days in response to the increased duration of Task 3.

Step 4: Watch a feeder buffer become a milestone

When the duration of Phase 1 Task 3 is increased to 15 days, the duration of the buffer task (originally 6 days) is fully consumed and the buffer task is now reflected as a milestone. The duration of the project buffer activity (in Phase 2) is reduced from 20 to 19 days.

Step 5: Baseline the plan with the buffers in place

This is the original project plan after adding the buffer activities, with a starting project buffer duration of 20 days, before exploring how the project buffer activity behaves as the schedule changes.

Step 6: Reschedule after a critical-path delay

The duration of Task 3 in Phase 2 is increased from 13 to 20 days and the project is rescheduled. The project buffer decreases from 20 days to 13 days, while the feeder buffer increases from 6 days to 13 days.

Step 7: Watch the project buffer fully consumed

The duration of Task 4 in Phase 2 is increased from 13 days to 20 days and the project is rescheduled again; the project buffer is now completely consumed and is reflected as a milestone.

Asta PowerProject is one of the only project scheduling tools that comes equipped with Buffer Management functionality out of the box. Do you want to experiment with Asta PowerProject’s Buffer Management functionality?

Ready to protect your own deadlines with Buffer Management?

Asta PowerProject builds project and feeder buffers right into your schedule. Try it yourself with a free trial.

Start a free Asta Powerproject trial
or call 1-800-931-1582